Saturday, December 17, 2005

Agile vs Big-Bang Project Delivery; Argument Solved








For years now, proponents of realistic IT approaches have been touting the importance of agile or spiral development. And aficionados of traditional "plan everything up front" approaches have been counteracting this by stating the need to agree to a fixed scope, and stay on time and on budget.

Several weeks ago I mentioned an excellent book that addresses this subject; Software Projects: Evolutionary vs. Big-Bang Delivery, by Felix Redmill. I finally finished reading it, and it points out how to resolve the differences, with a reasonable and sensible approach.

Again, the book is expensive (well over a hundred dollars), but can be found used for around fifty dollars on Amazon.com.

Below, I've paraphrased and summarized the key points:
  • Be sure to understand and state the business objectives up front. This is too high level for an adequate estimate, but it's a start.
  • Then conduct a feasibility study, analyzing as much detail as possible before authorizing the project. Most organizations skip this step, with bad effect. Aim for an aggressive but realistic target.
  • Beware of random constraints assigned by senior management, with no strategic cause. Most projects fail because they attempt to hold to unrealistic or arbitrary constraints. If necessary, document the risks of adhering to the arbitrary deadline and review with them. Negotiation tradoffs in scope, time, or cost as needed - or break the project into multiple phases.
  • It's still too soon for a definitive estimate, but the results of the feasibility study should be submitted as an "order of magnitude" estimate, along with risks and a plan for mitigating them. This becomes the business case for the project.
  • Make sure senior management understands that change is inevitable as the project progresses. But this change should be still be governed and weighed against the business objectives. Reassessment gates can be used to reset expectations of when the project ends.
  • Not all change should require governance. Project managers should have the leeway to use their own judgment to change tactics accordingly as long as it's within the business objectives. They should not just "follow procedures."
  • It should not be expected that all work will be done within the confines of the original document. For instance (and this is my example, not from the book), if implementing a purchased software project, a feasibility study would have been done before the software was purchased, configured, and tested. Upon configuration or testing, new discoveries/issues can (and probably will) occur. The only way to truly mitigate this is to do a pilot. Aside from that, expect changes.
  • This is a HUGE culture change for most organizations on the part of senior management. Without this level-setting, management will expect all work to be held to the original estimate, and judge success against it. This is the key reason why most IT projecst are seen as failures. We must manage stakeholder expectations (and that includes senior management).
  • Project progress should be weighed regularly against business objectives and not the completion of tasks. These objectives and the project's ability to meet them should be reassessed at each phase gate, with escalation of any variances to management. Again, this is the time to reset when the project ends, if necessary. This is also a huge culture change for senior management in most cases.
  • Scope should be revised as needed and documented at each step, so there's a record of the approvals and rationale for changes. Reasons of variations should be captured as lessons for future estimating.
  • Agile or evolutionary development is not an excuse to ignore change management. But change must be expected. To hold firm to a detailed schedule up front is not realistic for most IT projects.
  • Maintain close contact with users throughout the project to assure success.

This sounds like a sensible approach, but does require level-setting with management. Again, many project failures are a result of not setting the right expectations with management. Otherwise, a project can be a complete success, but management is dissapointed. This destroys morale and unfairly judges the project as a failure.

I recommend the book for those who want to learn more, as the book goes into far more details and offers examples, processes, etc. Here's the Amazon link...

http://www.amazon.com/gp/product/0471933430/102-4494239-8790520?v=glance&n=283155