Thursday, May 10, 2007

BT IT Project Model

One way to increase inventory turns is to decrease the lot-size in the supply chain space. For IT, reducing project size can have a similar effect. BT takes this approach to increase project throughput. ...

... "No IT project at BT is allowed to last more than 90 days. Mott says: If you can't deliver it in 90 days, then we're not doing it. So you need to pull teams together for 90 days, then a new team needs to form for the next project. " ...


Via Building: Agile Approach

Labels: , , , ,