Sunday, March 04, 2007

IT Project: Cutover Preparation

USAirways plans IT reservation systems cutover and emphasizes preparation for this major IT project
Mergers and acquisitions are common in today's markets. These corporate marriages often come with consolidation and integration. Eventually, information systems are consolidated. When systems touch customers, our risk antennae should perk up and we should prepare to minimize business impact. Preparation includes planning, temporary resources, a command center, practice through rehearsing, etc. Read about USAirways post-acquisition preparation for cutover to its common reservation system. ...

... "US Airways has been prepping for the mammoth IT project since the America West-US Airways merger closed in September 2005. " ...


Via Arizona Republic: US Airways IT Integration

Update: Via Bloomberg: USAirways Cutover Issues: "US Airways' kiosks at Charlotte and four regional hubs couldn't communicate with the reservation network for several hours after the systems were unified ... "

Labels: , , , , , , , ,

Monday, April 24, 2006

Project Failure Case Study; Maine's Medicaid System

Talk about a project disaster. As reported in an excellent article in CIO Magazine, the Maine Medicaid Claims System project is a case study of a project gone awry.

The project was undertaken to switch from their legacy systems to a new web-based system to process Medicaid claims and facilitate HIPAA compliance (Health Insurance Portability and Accountability Act of 1996). As a result of the failed project, Maine is now the only state in the union not in compliance with HIPAA.

System problems led to many claims ending up in limbo, leading to hundreds of calls from health care practitioners, nearly 300,000 patients being turned away, several dentists and therapists going out of business, and destroying Maine’s finances and credit rating.

So what went wrong?

Mistakes included the following:

  • Deciding to develop an entire system from scratch using unproven technology, while other states built a front-end onto their legacy systems
  • Caving to pressure from management to meet tight deadlines with inadequate resources instead of pushing for a realistic plan to begin with
  • Failing to notice why other bidders either didn’t bid or came in way higher (a sign that the schedule was unrealistic)
  • Hiring a vendor with no experience in developing Medicaid claims systems because they were the lowest bidder
  • Not having a Medicaid expert on the team, leading to errors in judgment
  • Underestimating the time needed to meet with subject matter experts
  • Competing with another major initiative (a department merger) for executives’ attention and resources
  • Skipping project management basics (including piloting, adequate end-to-end testing, staff and user training, etc.) due to looming deadline pressures
  • Failing to stop, regroup, and analyze the risks
  • Taking a “big bang” approach to cutover with no contingency or backup should something go wrong

Management’s response, of course, was to switch program managers, and issue stronger demands to have a smooth system, but none of the changes or demands made much of a difference. Consultants were brought in to prioritize the many problems, but still, the complexities proved too much. It wasn’t until a Medicaid expert was brought in that things began to gel.

Like many project failures, it’s easy to point to the project management (and certainly there are many shortcomings there in this case), but the organization must share the blame as well if it insists on unrealistic deadlines and leads by fear (fear of shareholders, fear of competition, fear of management, etc.). None of these variables can make an unrealistic schedule more realistic.

It's really very simple. Either adequate resources must be committed, the expectations lowered, or a more piecemeal approach taken (or all three, if applicable). In any case, the schedule must be realistic and risks need to be managed.

Here's the full article. It's well worth reading, as are the reader comments.

Maine's Medicaid Mistakes - Editorial - CIO

Labels: , , , , , , , , , , , , , , , ,

Thursday, February 02, 2006

Why Projects are Late; The Top Six Reasons

Here are the top six reasons why projects are late and what we can do about it...

1) Unrealistic Deadlines - As we've reported here before, this is one of the most frequently overlooked reasons for late projects---and unfortunately, often the last thing people look at.

Solution: It's imperative for a project manager to defend the right plan and not give in to pressure to sacrifice good principles. If necessary, negotiate to time-box the project into multiple phases.

2) Customer/Partner Availability - I've seen numerous project managers over the years talk about the challenges they face keeping a project on schedule when they're waiting on a customer or business partner to do testing or sign off on some deliverable.

Solution: Set milestones, monitor progress, and raise an issue if the lack of availability will cause a delay. If necessary, negotiate a new project baseline---which may be quite appropriate if the customer and/or steering team agrees that a delay is acceptable.

3) Resource Availability - There's nothing worse than putting together a reasonable schedule only to have your key resources pulled off into different directions, but it happens more often than we care to admit.

Solution: Try to obtain full commitment up front for your resources' time. Even so, unexpected conflicts will happen. Same as #2 above, set milestones, monitor progress, and raise an issue if needed. Again, negotiation may be necessary, which can result in getting your resources back or in setting a new project baseline to accommodate the new priorities.

4) Uncertainty - Especially in the IT field, uncertainty is a given. At any time, unexpected circumstances may cause project delays.

Solution: Use rolling wave scheduling, planning the whole project from a high level, but only the nearest 90-day horizon in detail. Try agile approaches as well, aiming for prototypes and frequent iterations. Ideally, pilot the project, and aim for vertical rollouts (one group at a time). Build contingency into your schedule for known risks. Most of all, manage stakeholder expectations.

5) Management Decision - Sometimes, management makes a conscious decision to delay a project, either for strategic needs, changes in priorities, or any number of reasons.

Solution: If the delay is a management or customer decision, a new project baseline should be saved, with current metrics based on that. Note that it's also important to keep the original baseline, as that offers a different set of measures (mostly around organizational alignment).

6) Poor Estimates - Sometimes a project is late simply because tasks were underestimated or omitted from the schedule. Although this is not always the cause of project delays (and rarely the only cause), it tends to be the first one people look at.

Solution: Build experience and capture historical data by project category and activity. If the data isn't categorized it won't be useful. Create and maintain checklists of items to consider. Build project schedule templates. The most frequently overlooked areas in IT are: training, data-loading, cutover preparation, system network testing, adequate QA testing, and documentation.